Under the "Pouring" WBS, add three activities: "Pump concrete," "Vibrate concrete," "Finish surface."
Build a 30-day concrete foundation schedule.
Link them: FS (Pump -> Vibrate) +0d lag, then FS (Vibrate -> Finish) +0d lag.
Click on the WBS tab -> Add WBS elements: "Site Prep," "Formwork," "Pouring," "Curing."
Assign a baseline by going to Project -> Maintain Baselines -> Assign Current Baseline.
This article serves as a roadmap. We will explore what makes a tutorial "verified," where to find legitimate PDFs, and a systematic breakdown of the core concepts you should expect from a high-quality Primavera P6 PDF tutorial. Before downloading any file, understanding the keyword "verified" is crucial. The internet is flooded with outdated tutorials (e.g., for P6 version 8.2, while the current is 22+), corrupted files, or guides written by non-practitioners.
Update progress: Set "Pump concrete" to 100% complete. Click F9 again. Watch Total Float recalculate.