Mep Work Progress Report Sample ❲PC EXTENDED❳

Copy the sample above, replace the data with your site's numbers, and take control of your MEP installation today.

[Image of insulated pipes on Level 3] / [Image of empty roof pad awaiting VRF units] 3. Electrical Works | Location | Activity Description | Unit | Planned Qty | Completed Qty | % Complete | Remarks | | :--- | :--- | :--- | :--- | :--- | :--- | :--- | | Basement | Cable Tray Installation (LV) | LM | 300 | 285 | 95% | Finishing by tomorrow | | Level 1 & 2 | Conduit Rough-in for sockets | No. | 120 | 120 | 100% | Completed - Ready for pulling | | Level 6 | DB (Distribution Board) Mounting | No. | 6 | 2 | 33% | Slow due to access issues | | External | Underground Earthing Grid | LM | 500 | 500 | 100% | Tested. Megger reading: OK | mep work progress report sample

[XX%] Status: [Green / Yellow / Red]